Project history

About us

TIMELINE DEVELOPMENT OF A COMPANY

Important milestones

3/2008 establishment of BOR Biotechnology, a.s. company
5/2009 beginning of project realization „Zero-emission technology for the production of electricity and thermal energy from the waste biomass” 
1/2011

selection of suitable location for the purposes of company’s business plan in the village Kozomín 

5/2011 rezoning of the former agricultural site in the village Kozomín
8/2011 obtaining a building permission in Kozomín (coming into legal force)
12/2011 launch of preparation for the realization of the project in the own area
2012

rehabilitation of the devastated soil of former agricultural area, terrain modification and adaptation

  project realization, of construction activities
6/2013 begin of the project’s energy technology part installation 
12/2013 completion of construction of the project’s halls
3/2014 completion of installation of the energy technology part
9/2014 starting test operation of “Energy Centre Kozomín (ECK)” – initial festive ignition
9/2015

Final building approval of ECK operation

Positive result of the EIA process of the "production of tissue" project

Future view

2016

authorizing decision of placement of  the paper mill 

2017

start of the construction of paper mill

2018 completation of paper mill building
2018

paper mill starting test operation